Hypercare Plan Example: A Filled-In Plan for an ERP Go-Live

A hypercare plan records who is covering which area after go-live, for how long, how issues escalate, and what has to be true before hypercare ends. The example below is from a fictional finance and procurement ERP go-live: fourteen areas, three weeks of tapering cover, each area with its own exit criterion and status.

The example

A services organisation of about 1,400 users goes live with finance and procurement modules on a Monday, four days after period end. Hypercare is planned as three weeks: week one on site with heavy cover, weeks two and three remote and thinner. The table is the version reviewed at the end of week three, with the status column filled in.

Severity definitions sit above the table and are shared with the service desk: severity 1 is a stopped business process with no workaround, severity 2 is a stopped process with a workaround, severity 3 is everything else. The organisation, dates and names are invented.

AreaWeek 1 coverWeeks 2 and 3 coverLeadEscalationExit criterionStatus at end of week 3
Accounts payableOn site, 08:00–18:00, 2 analystsRemote, 09:00–17:00, 1 analystAP Team LeaderFinance Systems ManagerTwo payment runs completed unaided; no sev 1 or 2 open for 5 working daysMet, 17 Apr
Accounts receivableOn site, 08:00–18:00, 1 analystRemote, 09:00–17:00, 1 analystAR Team LeaderFinance Systems ManagerOne full billing cycle raised and posted unaidedMet, 15 Apr
General ledger and postingsOn site, 08:00–18:00, 1 consultantRemote, 09:00–17:00, 1 consultantFinancial ControllerFinance DirectorTrial balance agrees to sub-ledgers for two consecutive weeksMet, 17 Apr
Bank interface and payment filesOn site, 07:00–19:00, 1 engineerRemote, on callTreasury ManagerFinance Systems ManagerTen consecutive payment files accepted first time by the bankMet, 11 Apr
Procurement and requisitionsOn site, 08:00–18:00, 2 analystsRemote, 09:00–17:00, 1 analystProcurement ManagerHead of ProcurementRequisition-to-order volume back to pre-go-live weekly averageNot met, extended to 25 Apr
Supplier master dataOn site, 09:00–17:00, 1 analystRemote, 09:00–17:00, sharedMaster Data LeadFinance Systems ManagerOpen data defects under 10, none blocking paymentNot met, 14 open at 18 Apr
Expenses, including mobile appRemote, 09:00–17:00, 1 analystRemote, 09:00–17:00, sharedExpenses AdministratorFinance Systems ManagerOne full claim and reimbursement cycle completedMet, 16 Apr
Reporting and extractsRemote, 09:00–17:00, 1 developerRemote, 09:00–17:00, sharedReporting LeadFinance Systems ManagerAll 22 agreed reports produced and reconciled onceNot met, 19 of 22 signed off
Payroll interfaceOn site for run only, 1 engineerOn site for run onlyHR Systems LeadHR DirectorOne payroll run posted with zero manual correctionMet, 24 Apr
Access and authorisationsOn site, 08:00–18:00, 1 analystRemote, 09:00–17:00, sharedIT Security AnalystHead of Information SecurityAccess requests inside standard SLA for 5 working daysMet, 17 Apr
Period-end closeNot applicable in week 1On site for close, 2 consultantsFinancial ControllerFinance DirectorFirst close completed within the published timetableDeferred, first close is 30 Apr
Print and output managementOn site, 09:00–17:00, 1 engineerRemote, on callIT Operations ManagerFinance Systems ManagerAll document types printed correctly at all three sitesMet, 14 Apr
Service desk scripts and knowledgeOn site, 09:00–17:00, 1 analystRemote, 09:00–17:00, sharedService Desk LeadIT Service ManagerFirst-line resolves 60% of tickets without escalation for 5 daysMet, 18 Apr
Vendor product supportNamed consultant, 08:00–18:00Named consultant, 4 hours dailyVendor Engagement ManagerCommercial LeadOpen vendor tickets under 5, none severity 1 or 2Not met, 7 open at 18 Apr

Reading the example

Area

Rows follow business processes rather than the project workstreams that built them. Accounts payable is a row because a payment run either happens or does not; the interface, the data and the authorisations behind it are separate rows because they have separate owners and fail in separate ways. Fourteen rows is what it takes to cover a two-module go-live without any of them meaning "everything else".

Cover, week by week

Each cell says where, when and how many. The taper is visible: on site becomes remote, two analysts become one, and several areas become "shared", meaning one person covers three rows. Two rows break the pattern deliberately — the bank interface runs 07:00 to 19:00 in week one because payment files leave early, and the payroll interface has cover only on run day, which falls outside the three-week window entirely.

Lead and escalation

Two names per row: the person handling it and the person it goes to when it is not being handled. The escalation column is not the sponsor. It is deliberately one level up, and only the areas with financial or regulatory consequence route to a director.

Exit criterion

The load-bearing column. Each is written as an observable event with a number or a cycle attached: two payment runs, ten accepted files, a trial balance that agrees twice, one payroll run with no manual correction. Criteria written per area allow hypercare to end in pieces rather than all at once, which is what actually happens. The Cutover Runbook and Hypercare Pack carries these on their own tab with the same structure.

Status

The record of what was true at the review, including where it was not. Four rows had not met their criterion at the end of week three, and one — period-end close — could not have, because the first close falls after the planned window. That row is the reason a hypercare plan is worth writing before go-live rather than during it: the date of the first close was known months in advance, and a three-week window was never going to contain it.

What this example leaves out

There is no ticket log here. Volumes, ages, severities and who is fixing what live in the defect tracker; this plan records the shape of the cover and the conditions for ending it. Reporting the two together each week is what the weekly status report is for.

It carries no cost. Three weeks of consultants, on-site presence and vendor cover is a real number, and extending an area — as procurement and supplier data both were — spends money that was usually not in the forecast. The plan shows the extension; the budget tracker shows what it cost.

It does not define the service that follows. Exit criteria say when hypercare stops, not what business as usual looks like on the other side: support tiers, ticket routing, standing costs, who owns the system. That is a handover, and it belongs with closure and handover rather than here.

Nor does it decide anything. When four areas miss their criteria at week three, whether to extend, accept and transfer the remainder, or split the difference is a judgement for the sponsor and the service owner. The plan records the criteria, the status and the extension; the reasoning is written down elsewhere. Hypercare after go-live covers scope, duration and exit criteria in general terms.

Questions

How long should hypercare last?

Long enough to cover at least one full instance of every critical cycle, which in a finance go-live usually means a period-end close. Three weeks is common; where close falls outside it, the plan either extends or covers close separately.

Can different areas exit hypercare at different times?

Yes, and in practice most do. Criteria written per area allow cover to be withdrawn as each one is met, rather than holding an entire team in place for the slowest process.

Who staffs hypercare?

Usually a mix: the project team who built it, the operational team who will keep it, and named vendor support. The plan matters most where those three groups meet, because that is where an unowned issue sits longest.

What is the difference between hypercare and warranty?

Warranty is a contractual obligation on a supplier to fix defects for a period. Hypercare is an operating arrangement covering the whole organisation, including internal staff and processes, and usually runs shorter.

Examples · All 36 templates