Project Status Report Example: One Week of an ERP Migration

A weekly project status report states the position on schedule, scope, budget, resource, risk and quality, the milestones, and the decisions being asked for. The example below is week 14 of a fictional ERP migration: seventeen lines, each with a RAG value, the position, the movement since last week and an owner.

The example

This is week 14 of a fictional ERP migration at a three-site manufacturer, reported on Friday 11 April for a go-live on 18 May. Currency figures are in thousands and millions of pounds. The report is one page because that is what gets read; the detail behind each line lives in the RAID log, the plan and the budget tracker, and the report points at them rather than reproducing them.

ItemRAGPosition this weekChange since last reportOwner
Overall statusAmberDelivery still tracks to the 18 May go-live. Two things are keeping it amber: purchase order data quality and training completion.Amber, third weekProgramme manager
ScheduleAmberDry run 3 moved from 17 to 21 April so the corrected purchase order mapping can be rebuilt and retested. Go-live date unchanged; float down from 9 to 5 working days.Green to amberProgramme manager
ScopeGreenTwo change requests approved this week: CR-014 (nine additional legacy reports) and CR-015 (barcode label layout). Both inside the approved contingency.No changeProgramme manager
BudgetAmberSpend to date 1.42m against a 1.38m plan. Forecast at completion 2.31m against an approved 2.25m. The variance is the integration development in CR-014.Green to amberFinance business partner
ResourceAmberFinance workstream loses two analysts to year-end close from 13 April. Cover agreed for one; the second post is with the recruiting agency.No changeFinance workstream lead
RisksAmberFour red risks open, unchanged from last week. The payroll interface single-developer risk (R-01) closes when the handover pack is accepted, expected 25 April.No changeProgramme manager
IssuesRedIntegration environment availability remains the largest issue: available on 6 of the last 10 working days. Dedicated build starts 14 April.Amber to redInfrastructure lead
DependenciesRedChart of accounts sign-off from the finance transformation project (D-02) is 5 weeks old with no committed date. Escalated to the programme board this week.No changeProgramme manager
QualityGreenUAT: 214 of 218 cases passed. Four deferred by agreement to the June release. No severity 1 defects open; two severity 2 with fix dates.No changeTest manager
Milestone - UAT exitCompleteAchieved 04 April, two days later than planned. Exit report signed by the test manager and both workstream leads.Was at riskTest manager
Milestone - Dry run 3At riskPlanned 21 April. Depends on the integration environment being stable from 16 April; that is the current concern.Was on trackData lead
Milestone - Training completeAt riskPlanned 09 May. 312 of 502 users trained. Shift patterns at two sites make the last 60 users difficult.No changeChange lead
Milestone - Go/no-goOn track11 May. Criteria agreed in February, evidence owners named, no changes requested this week.No changeProgramme manager
Milestone - Go-liveOn track18 May, subject to the go/no-go decision. Weekend cover booked; freeze notice drafted.No changeProgramme director
Decisions required-1. Approve the 60k budget variance from CR-014. 2. Agree the approach for training the last 60 shift workers: extra weekend sessions, or a waiver with training in hypercare week 1.New this weekProgramme board
Decisions taken-Finance UAT window moved to 06-24 April (finance director, 12 February). Severity definitions agreed at the test board (19 February).-Programme manager
Next period-Rebuild and test the purchase order mapping, stabilise the integration environment, execute dry run 3, push training numbers, sign off the hypercare rota.-Programme manager

Reading the example

What makes the amber lines credible

Three lines are amber and two are red, and the report is more believable for it. The pattern that destroys credibility is the one where a project reports green for eleven weeks and red in week twelve. Anyone who has sat on a steering committee has seen it, and the effect is that green stops meaning anything at all.

The schedule line here does the thing that most reports avoid: it says the milestone moved and the go-live date did not, and it says what was consumed to achieve that. Float dropping from nine days to five is the sentence a reader should react to. Reporting only that the date is unchanged is technically true and materially misleading.

The budget line shows the same discipline. It gives spend to date against plan, then forecast at completion against approval, because those answer different questions. Spend to date says what has happened; forecast at completion says whether there is a problem. A report that shows only the first is describing the past. The reasoning behind that is set out in the project status report guide.

Who this report is for

This one is written for a programme board that meets monthly and reads a weekly email in between. It is deliberately not a steering committee pack: there are no slides, no financial breakdown by workstream and no risk heatmap. Those belong in the monthly pack, structured around the decisions the committee is being asked to take, as described in the steering committee report guide.

The audience also explains the length. Everything a reader needs to act is in the first four lines; the milestone rows are for the person who checks dates; the decisions rows are the call to action. A report that has to be read from top to bottom before anything can be understood has ordered itself for the writer rather than the reader.

What this example leaves out

The workbook version of this page, with the RAG dashboard and milestone view built in, is the weekly IT project status report. The same content as slides for a senior audience is the IT project status report deck.

Questions

How long should a weekly status report be?

One page. Everything a reader needs to act on belongs in the first few lines, with detail left in the plan, the RAID log and the budget tracker. Length is what stops reports being read, not complexity.

What should the RAG values mean?

Whatever the project has written down and applies consistently. In the example green means no intervention needed, amber means being managed with a named action, and red means help is required from outside the project.

Should a status report include decisions?

Yes. The decisions required line is usually the reason the report exists. State each one as a choice, with options, addressed to a body that can actually decide it.

Is a weekly report the same as a steering committee pack?

No. The weekly report keeps a working audience current; the steering pack is built around the decisions a committee is being asked to take, usually monthly, with financial and risk detail the weekly report leaves out.

Examples · All 36 templates